Company setup · 1 of 14
Assign your QS reviewers
Set up your review team in Team & Licences. Use the Manager/QS role for the colleagues carrying out QS reviews, with the appropriate Full licences. You can have multiple QS reviewers.
The Team & assignments tab shows the sample reviewers and their roles.
Engineer · 2 of 14
The engineer submits the certificate
Complete and check the certificate, then use the submission button on the certificate summary to send it for QS review.
Choose Send for QS review, or Submit for QC in the summary toolbar.
QS · 3 of 14
Find the certificate in the QS queue
The submitted certificate appears under Awaiting review in the QS review queue. The address, client and engineer help the QS find the right work.
The sample submission is ready for review.
QS · 4 of 14
Start the review
Open the certificate and select Start Review. This claims the review for that QS; simply opening it to look does not claim it.
Start Review is the point at which the QS takes responsibility for this review.
Another QS · 5 of 14
One active reviewer. Multiple QS users.
Once a QS starts the review, it becomes read-only for the other QS reviewers. Their review controls are greyed out or unavailable, preventing two people from changing the same review at once.
This is the view for another QS while the review is already held.
QS · 6 of 14
Leave a note against the distribution board
Use the notebook to record what needs checking against the relevant certificate section. Here the QS asks the engineer to confirm the circuit descriptions against the board labels.
The app calls this panel QC Notebook. The note stays with its section.
QS · 7 of 14
Add a second note to the inspection schedule
Move to another section and add its own note. Separate comments keep each correction in context instead of mixing everything into one message.
This example asks the engineer to check an inspection outcome and explain any limitation.
QS · 8 of 14
Return the certificate for amendments
Save the section notes, then select Reject to return the certificate to the engineer for correction. The notes explain what needs attention.
Reject returns the certificate for changes; it does not delete it.
Engineer · 9 of 14
The engineer sees the returned work
The certificate appears in the engineer’s certificate list as Returned for changes. Open it and work through the notes attached to the affected sections.
The status distinguishes returned work from certificates still in progress or complete.
Engineer · 10 of 14
Correct the issue and resolve the note
Make the actual amendment in the relevant certificate section, save it, then mark the note as resolved. Repeat for each issue. Marking a note resolved does not make the amendment for you.
Open circuit entry, amend the description and save. Then mark the section note as resolved.
Engineer · 11 of 14
Resubmit for QS review
After making and saving the amendments, submit the certificate again. The QS can review the corrected work and the resolved section notes.
The certificate returns to the review workflow for a fresh decision.
QS · 12 of 14
Check the amendments and approve
The QS checks the changes against the section notes. If further changes are needed, return it again. When satisfied, select Approve to approve the certificate.
Resolved notes are a record of the engineer’s response; the QS still checks and makes the approval decision.
Engineer · 13 of 14
Complete in the engineer’s list
After QS approval, the certificate is shown as Complete in the engineer’s certificate list. The completed work stays with the certificate record.
The same sample address and reference make the finished certificate easy to recognise.
QS · 14 of 14
Approved in the QS’s list
The reviewing QS can find the certificate under Approved by me in the QS review queue.
Approved by me shows the certificate approved by this reviewer.